Projects
Projects are derived from LDP/600 Resources/LDP Disciplines and have some Objective that requires some set of LDP/600 Resources/Tasks to complete. These Projects should make progress towards or uphold some Pillar from the parent discipline.
Projects should strongly fit into one Discipline, and if it seems a Project could fit in multiple, the Disciplines need to be reorganized to prevent overlapping dependency, where too many items from one discipline belong in another Discipline. Just combine the two or figure out some other way to have them clearly different.
Scoping
Projects will be of varying sizes and should be longer than 2 hours, as this is the arbitrary maximum length of LDP/600 Resources/Tasks. Since tasks make up a Project, it’s a given that Projects should be bigger than a Task.
While there isn’t a real maximum on how big a Project is, it’s suggested to be no longer than a month, averaging several weeks. This duration is based on the general duration of a Sprint. And this is under the assumption that this Project is the ONLY thing you’re working on. Plan your Projects and focus according to your available time.
Relations and Placement
Projects should be placed within a dedicated projects folder.
Tasks are largely derived from Projects to make leeway towards meeting the Objective, which in term, meets the discipline’s pillars and/or Dynamic.
Abstract
Explains the context of the project. Generally discusses the following.
- Origins of what prompted this project
- Why this needs to come into fruition, why what follows that is also important… etc
- Other things that can result from this project
Objective
All Objectives should minimally answer the following questions.
- What will come to fruition?
- How? What main methods or tools will be used to do this?
Completion Criteria
Unlike LDP/600 Resources/LDP Disciplines, Projects should eventually come to an end and shouldn’t run any longer than 1 month. Since there usually isn’t a time-based ending point (True Deadline), an end must be defined through some other means.
For Projects, a Completion Criteria is a well-defined checklist that culminates in a shift in the environment or the creation of a deliverable.
Well-Defined as in, requirements can be clearly answered Yes
or No
if they have been met. These Requirements should align with the Core.
While there is no hard limit of Completion Criteria count, it should be noted that these are essentially groupings for Tasks. Having too much Completion Criteria may hint at a project that may take longer than 1 month.
All Projects should have Completion Criteria, but the Objective should come first.
Alignment
Projects should be routinely reviewed to ensure that they progress towards some Pillar denoted under its corresponding Discipline. It’s suggested to do this review weekly.